Pipe connections to/from Water buildings(Early Start DLC) not working properly
Only front pipe connections on early start dlc are usable, sideways connections are blocked by the building itself, lowering the pipe does not fix.
On the early start water treatment plant the issue is similay, although one can barely fit in pipes with lots of effort.
Connection points on both buildings are situated under the building itself, probably causing that problem.
< >
Showing 1-9 of 9 comments
esbenmf 12 Jun @ 4:44am 
Confirmed.
Kaia 12 Jun @ 6:28pm 
+1

I was able to fiddle around the water treatment plant to make pipes go in.

The water well you start with though has all ports inaccessible, except the front 2.
same. it's actually so damn irritating. particularly the treatment plant, resisting the urge to just turn off the water system all together. i mean SURELY this had to go through some sort of testing right????
Rach 14 Jun @ 1:53am 
Originally posted by The duckman:
same. it's actually so damn irritating. particularly the treatment plant, resisting the urge to just turn off the water system all together. i mean SURELY this had to go through some sort of testing right????

No, devs stopped testing altogether it seems. We must do that ... and then wait and hope!
If You start from short section it is easy to get out of building zone.
3division  [developer] 17 Jun @ 2:03am 
will be fixed into new version.. thank you!
Kaia 17 Jun @ 4:08am 
Will the outlandish cost of the early start treatment plants/well be fixed as well?
3division  [developer] 17 Jun @ 6:06am 
Originally posted by Kaia:
Will the outlandish cost of the early start treatment plants/well be fixed as well?
Yes! :)
Kaia 17 Jun @ 6:29am 
Originally posted by 3division:
Originally posted by Kaia:
Will the outlandish cost of the early start treatment plants/well be fixed as well?
Yes! :)